Subcontractors Guide

Subcontractors — engaged on the record, paid on the clock

A subcontractor record in Constructum names the job, the company, the trade and the contact, and tracks the engagement through Active → Mobilised → Working → Completed → Paid out, with Default notice and Stood down as the exception states nobody wants and every professional operation needs.

The payment cascade is law, not goodwill

Under Alberta’s Prompt Payment and Construction Lien Act, payment flows down the chain on statutory clocks: the owner pays the contractor within 28 days of a proper invoice (or disputes formally within 14), and the contractor must pay its subcontractors within 7 days of receiving that payment. “Paid out” as the terminal state of a subcontractor record exists because of that cascade: an engagement is not finished when the work is done — it is finished when the sub has been paid, on the record, inside the clock. Subcontractors hold lien rights of their own under the Act; prompt, recorded payment is how a general contractor keeps those rights theoretical.

Terms in writing, before mobilisation

The people terms are part of the professional standard here: scope, rates and payment terms in writing before anyone mobilises; no fee charged to any worker or trade for access to the work; no hidden deductions from what was agreed. A record that shows the engagement from Active to Paid out, with the job named on it, is the evidence that the operation runs that way — and it is the record a good trade checks, in substance, before committing its crews to your next job.

Default and stand-down, handled straight

When a subcontractor cannot perform, the record says so — Default notice issued, or Stood down — while the work is re-covered through the schedule. What the record never does is quietly disappear an engagement that went badly. The history is how the next engagement decision gets made on evidence, and it is also the subcontractor’s protection: a trade that performed has a completed, paid-out record that says so in the general’s own system.

Worked example: Prairie Grid Electrical Ltd was engaged on the CHAIN Northgate Yard Expansion as the electrical subcontractor and mobilised to Working on the job’s record.