RFIs — questions that cannot hang
An unanswered question on a live job is a cost looking for somewhere to land: a crew idle, a pour delayed, or — worst — a decision made unilaterally at the workface and argued about at claim time. The RFI module puts every request for information on the job record: the question, who raised it, who it is assigned to, when the answer is due, the answer, and who gave it. Due dates are not decoration — an open RFI past its date surfaces in your work panel as overdue work, in front of the people who can move it.
How an RFI moves
Open → Answered → Closed. Raised by whoever hits the ambiguity — superintendent, foreman, sub — and assigned to whoever owns the answer. The answer is written on the record, attributed, and the RFI closes when the raiser accepts it. An RFI raised in error is Withdrawn, or Void with the reason kept. Nothing is deleted: the question-and-answer history of a job is part of how its decisions get audited.
An RFI answer is not a change order
The discipline that protects both sides: an RFI clarifies the work; it does not reprice it. Where an answer changes scope, cost or time, the change still goes through Change Orders — priced, approved and instructed before the changed work proceeds. Keeping the two records separate, and linked by the job, is what stops the most common variation dispute in the industry: “the RFI answer told us to build it” against “the RFI never authorised the cost.” Here, both records exist and both say exactly what they say.
What good looks like
Questions raised the day they are found, not the week they become delays. Owners and due dates on every one. Answers that cite their basis — a spec section, a memo, a revision — so the answer can be checked, not just believed. And a work panel that shows overdue RFIs before they become claims.
In the worked example on this site, RFI-001 (record #80) was raised on Job #42 by the site superintendent after change order CO-1: confirm the bearing elevation for the deepened grid C footing. The design lead answered on the record — bear at 2.1 m below grade per the geotechnical memo — and the RFI was closed, with the question, the answer and both names on the job file.