Daily Logs Guide

Daily Logs — the day, on the record

The daily log is the oldest instrument on a construction site and still the one everything else gets tested against: who was on site, what the weather did, what got built, and what got in the way. In Constructum it is a module, not a notebook — one record per job per day, filed by the foreman, carrying crew count, the trades present by company, weather, the work completed in plain language, and the day’s delays or issues. Because it names the same job as the schedule, the drawings and the claim, it stops being a diary and becomes evidence the rest of the system can use.

How a log moves

Draft → Filed → Reviewed. The foreman drafts the log during the day and files it at day’s end; the filed log then waits in the site superintendent’s approvals — the foreman answers to the superintendent — and the superintendent’s review closes the day. A log still at Filed is a day nobody has signed off. Two exception states cover the days construction actually has: Weather day and No-work day — named, dated, and on the record, so a lost day is documented when it happens rather than argued about at extension-of-time time.

What the log feeds

Three readers live off the same entries. The project manager certifies progress claims against them — the claim says what was earned; the logs say what happened, day by day, in the period claimed. The schedule’s percent-complete is judged against what the logs report, not against optimism. And in a delay dispute, the sequence of filed logs — weather, crew, stoppages — is the contemporaneous record Alberta courts and adjudicators actually weight, because it was written when the facts were fresh and before anyone knew a dispute was coming.

What good looks like

The foreman answers to the site superintendent, and the Daily Log is where that line runs: the foreman files the log, it waits in the superintendent’s approvals, and the superintendent’s review (Filed → Reviewed) closes it. A day nobody reviewed is a day still open. Filed the same day, every day, by the person standing on the work. Crew and trades named by company, so a subcontractor’s presence on a given day is checkable. Work completed written as physical fact — areas, quantities, systems — not effort. Delays recorded on the day they bite, with the cause, whether or not anyone yet knows who pays for them.

In the worked example on this site, the 7 November log for the Northgate Yard Expansion (record #96) reads: crew of 9; electrical (Prairie Grid), concrete and formwork on site; clear, −2 °C; electrical rough-in continued in grid C and footings poured on the grid D line; no delays. It was filed the same day — and that afternoon’s inspection finding flowed straight into the Deficiencies module (see that guide).