Drawings Guide

Drawings — the current set, and nothing else on site

More construction disputes start with a crew building from a superseded drawing than from almost any other single cause. The Drawings module is the register that prevents it: every drawing on the job — number, discipline, revision, who issued it, when, and who it was distributed to — with one discipline enforced by the record itself: for each drawing number there is a current revision, and the current revision is the only one anyone builds from. Superseded revisions are not deleted. They stay on the register, readable, because the work built from them is real and the record of which revision stood when is evidence.

How a drawing moves

Draft → For review → Issued → Current. A revision is marked Current when it becomes the set the site works from; issuing the next revision and marking it Current moves the earlier one to Superseded. A drawing entered in error is Void — marked, with the reason on the record. The register shows the state of every revision at a glance, so a superintendent answering “what are we building from?” never has to guess, and the distribution list on the record shows exactly who received each revision — a revision that was issued but never distributed is a known failure mode, visible here instead of discovered at inspection.

Why the discipline is legal, not clerical

Under Alberta’s Safety Codes Act, work is inspected against the design the permit was issued on. When a change order alters the work, the drawing revision that carries the change is part of the contract record — which is why this register links every revision to its job and records what it supersedes. If a deficiency or a dispute turns on what the drawings said at a given date, the register answers from the record, not from memory or a flattened email thread.

What good looks like

One register per job, kept current the day a revision issues. The current set identifiable in seconds. Superseded revisions preserved, never circulating as prints nobody collected. Distribution recorded, so “I never got rev 2” is checkable rather than arguable.

In the worked example on this site, drawing A-101 (foundation plan) for Job #42 was issued as revision 1 and marked Current (record #78); when change order CO-1 deepened the grid C footings, revision 2 was issued against the same drawing number, marked Current, and revision 1 moved to Superseded (record #79) — the site set is revision 2, and revision 1 remains on the register.