Materials & Deliveries — from order to accepted, with the exceptions priced in
A materials record names its job, the material, the supplier, the quantity and the delivery date, and it walks the physical truth of a delivery: Ordered → Confirmed → In transit → Delivered → Accepted. The exception states are where the money is protected: Short delivery, Damaged, and Rejected.
Acceptance is the moment that matters
Delivered is not accepted. Acceptance is the check at the gate — count, condition, and conformance against the order — and it is the state the record should sit in only when that check has happened. A short delivery recorded the day it arrives, with the quantity as-received against the quantity ordered, is a supplier credit recovered without a fight. The same shortage discovered at month end, after the invoice is paid, is a donation. Rejected material leaves the site with its record intact, so a second delivery of the same wrong product is recognised as a pattern, not a surprise.
Deliveries feed the claims
Materials on site are a standard component of certified work in a progress claim — but only materials actually delivered and accepted should be claimed. Because the delivery record sits on the same job as the claim raised in Accounting, the claim’s basis is checkable line by line: what the estimate priced, what was ordered, what arrived, what was accepted. Suppliers who deliver complete and on time build a record here that wins them the next order on evidence rather than habit.
Dates are commitments in both directions
The delivery date is the supplier’s commitment; the overdue view treats a missed delivery like any other missed commitment on the job — visible the day it slips, while a phone call can still fix the sequence, not at the pour. Order against the schedule: material arriving three weeks early is a storage and damage problem wearing the costume of efficiency.
Worked example: 40 tonnes of 15M rebar for the CHAIN Northgate Yard Expansion moved Ordered → Confirmed → In transit → Delivered → Accepted against its delivery date, on the job’s record.