Jobs & Projects — the job file everything else hangs on
Every record in Constructum names its job. The Jobs module is where that job exists: client, site, contract value, completion date, and where the work stands. Estimates point at it, schedules are built on it, subcontractors, materials and equipment are committed to it, safety and inspection records are filed against its site, change orders price against its contract value, and the progress claim in Accounting is raised from it. Open a job and you can reconstruct the whole engagement without asking anyone what happened.
How a job moves
Tender → Won → Mobilising → On site → Practical completion → Defects period → Closed. Two exception states sit alongside the line: On hold (work suspended — funding, permits, weather season, client instruction) and Disputed (the record stays open and readable while the dispute runs; nothing is quietly closed over a disagreement). Closing a job is an approval state: it should mean the file is complete, not that someone stopped looking at it.
The contract value is a carried figure
A job is opened from its won estimate, at the estimate’s value. From there the contract value only moves through change orders — each one priced, approved and instructed in the Change Orders module — so the current contract total is always estimate plus approved changes, never a number someone re-typed. Progress claims are percentages of that total, which is why the discipline matters: a claim against a wrong base is wrong everywhere downstream.
Completion, defects, and the Alberta holdback
Practical completion is a factual state: the work is fit for its intended use, with deficiencies listed rather than argued about. The defects period that follows is the contractor’s window to make good — track it here, against the completion date, with the final inspection sign-off filed in Inspections.
Money at closeout runs on Alberta’s Prompt Payment and Construction Lien Act: the standard holdback is 10% of the contract price, held against lien claims. Holdback release follows the Act’s timelines and the expiry of the lien period — it is not a discretionary favour at project end. The job record’s value, completion date and status are the facts the holdback calculation stands on, so they are kept exact.
What good looks like
One job record per contract. The value carried from the won estimate. Status that matches the site, not the optimism of the last meeting. And at closeout, a job file — estimate, schedule, safety record, inspection sign-offs, change orders, claims, invoices — complete enough to hand to the client, an auditor, or a court without reconstruction.
In the worked example on this site, Job #42 (CHAIN Northgate Yard Expansion) was opened at its won estimate figure, carried one approved change order, and closed through practical completion and the defects period with its full file in the vault.